Factors Influencing Time Performance of Road Construction Projects in Bauchi Metropolis, Bauchi State, Nigeria
DOI:
https://doi.org/10.64321/jcr.v3i4.14Keywords:
Road Construction, Time Performance, Project Delays, Bauchi Metropolis, Cost OverrunAbstract
Time overrun remains a critical challenge in the Nigerian road construction sector, contributing to cost escalation, project abandonment, and poor service delivery. In Bauchi Metropolis, several flagship road projects have recorded significant delays despite high budgetary allocations. This study evaluated the key factors influencing time performance of road construction projects in Bauchi Metropolis. A census approach was adopted with 116 questionnaires administered to clients, consultants, and contractors involved in ongoing projects. A total of 113 responses were retrieved and analyzed using descriptive statistics, mean score, and Relative Importance Index (RII). Findings revealed that the top five factors influencing time performance were: ineffective planning and scheduling by contractors (RII = 0.829), poor site management and supervision (RII = 0.827), difficulties in financing projects (RII = 0.794), poor communication and coordination by contractors (RII = 0.786), and delay in progress payments by owners (RII = 0.878). Among owner-related factors, delay in payment and poor coordination were most significant. Among external factors, subsurface conditions and delay in utility services ranked highest. The dominant effects of time performance failure were time overrun (RII = 0.903), cost overrun (RII = 0.850), project abandonment (RII = 0.796), and disputes (RII = 0.775). The study concludes that contractor-related and owner-related factors are the primary drivers of delays in Bauchi Metropolis. It is recommended that contractors strengthen planning and resource mobilization, while clients ensure timely payments and prompt decision-making to improve project delivery time.
References
G. Agyekum-Mensah and A. Knight, "The professional’s perspective on the causes of project delay in the construction industry," Engineering, Construction and Architectural Management, vol. 24, no. 5, pp. 828–841, 2017. doi: 10.1108/ECAM-03-2016-0085
A.F. Adebayo, F. F. Funke, and A. O. Mustafe, "A study on the effects of construction project delays in Somaliland construction industry," 2020.
BASIDMA, _Report on the causes of delay and cost overruns in construction of road projects in Bauchi State, Nigeria_, 2024.
S. Bounthipphasert, N. Shozo, O. Toshihiro, and N. Takafumi, "Causes of delays in road construction projects in Laos," Global Journal of Researches in Engineering: E Civil and Structural Engineering, vol. 20, no. 3, 2020.
A.S. Abdilkerim, M. S. Hamed, A. Abubeker, and A. H. Abdurahman, "Causes and effects of project delay in public construction projects in Ethiopia," 2023. doi: 10.21203/rs.3.rs-2680680/v1
E. J. Mamman and E. R. Umesi, "Causes and effects of delay on public construction projects delivery in Nigeria," African Scholar Publications and Research International, vol. 24, no. 4, 2022.
E. O. Aiyewalehinmi, B. D. Oluyemi-Ayibiowu, and J. N. Okwueze, "Evaluation of factors causing delay in building construction projects in Ondo State, Nigeria," European Journal of Engineering and Technology, vol. 7, no. 2, 2019.
J. Aladayleh, G. Ferrer, S. Pablo, B. Fuentes, and L. José, "Factors influencing construction projects delay: An exploratory study at a Jordanian public university," in Proc. 24th Int. Congress on Project Management and Engineering, 2020.
Y. B. Firdissa, "Causes and effects of delay in Oromia Roads Construction Projects Pertinent to Oromia Roads Authority Road projects," 2018.
A.B. Ghanim, "Study and assessment of causes and effects of delay in large public construction projects in Jordan," International Journal of Applied Engineering Research, vol. 13, no. 8, pp. 6204–6210, 2018.
R. Asish and P. Pratheeba, "Study on construction sequence delay for road infrastructure projects," IOSR Journal of Mechanical and Civil Engineering, vol. 12, no. 2, pp. 15–21, 2015.
M. B. Bouraima, Y. Qiu, C. K. Kiptum, and K. M. Ndiema, "Evaluation of factors affecting road maintenance in Kenyan counties using the ordinal priority approach," Journal of Computational and Cognitive Engineering, vol. 2, no. 3, pp. 260–265, 2023. doi: 10.47852/bonviewJCCE2202272
R. F. Aziz and A. A. Abdel-Hakam, "Exploring delay causes of road construction projects in Egypt," Alexandria Engineering Journal, vol. 55, no. 2, pp. 1515–1539, 2016. doi: 10.1016/j.aej.2016.03.006
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Ahmed Faruk

This work is licensed under a Creative Commons Attribution 4.0 International License.